Piers, docks, jetties, walkways, and similar structures on helical piles are highly practical and are becoming increasingly popular, including in Tambov and the Tambov Region. The rules for selecting helical piles for piers, jetties, and walkways (for simplicity, we will refer to all of them as piers below), and the construction process, are largely the same as for other pile applications. However, there are some specific points to consider.

First, piers are easiest to build in winter, once a stable !!! ice cover has formed.

Installers can move freely around the construction site and carry out all the necessary tasks. Setting out on the ice is easy and accurate. Powered equipment such as the Hercules helical pile installation unit can be used, making the work considerably easier.

In other words, all the conditions are in place for turnkey construction. Preparation for the installers' arrival generally consists of clearing an access route so that a GAZelle van can get reasonably close to the site. In our experience, boards, panels, or similar materials sometimes need to be prepared for the installation, because marshy banks often do not freeze: both installation and simply moving around can be difficult. The only obstacles are severe frost, exceptionally thick ice (we have even built through 0,7 m of ice! This is true: the dam was opened in winter, the ice that had already formed dropped, the dam was closed, and water above the old ice froze again), or simply the absence of ice. Installing a pier on helical piles in winter will also cost you less than struggling in summer, but more on that below.

Summer is not an insurmountable obstacle to construction. But judge for yourself. Rigs of the УБМ type can be used to screw in helical piles.

However, such a rig cannot reach the water everywhere: the bank may be marshy or steep, the boom may not be long enough, and so on. Can you arrange conditions like those in the photo, including covering the cost?

Pontoons or boats have to be used. Accurate installation is hardly possible. Installers generally cannot avoid getting into the water, and in our latitudes this is uncomfortable, to say the least, without wetsuits for most of the summer season. What if the water is deep? Suppose you have now screwed in the piles this way. Next comes the bracing. Need we go on? We will not even discuss manual installation: in most cases it is practically a gamble. Are your conditions like those in the photo? You are lucky… But welding in the water and similar tasks still lie ahead…

Our conclusion: it is better to put aside the idea of installing piers and similar structures on helical piles in summer. Instead, prepare in advance for winter work: measure the depths (at 1 metre intervals), investigate the bottom by the means available, and, where possible, clear reeds and similar vegetation from the water and adjacent bank.

If you engage WINTTEK to manufacture the piles and perform the installation, agree all preliminary details in advance and pay for the pier materials and installation. The price will then remain fixed until installation, and the work will be carried out at a convenient time during the period of stable ice cover. You can also save money: traditionally, a promotion runs from 1 December to 29 February, offering a discount of up to 10% on piles purchased with installation. See Information–News and Information–Promotions for details.

Second, understand that the main vertical loads on a pier come from the rise of the ice in spring rather than the weight of the pier and all its components. Horizontal loads come from moving ice.

The pile selection rules follow from this. On enclosed bodies of water, the ice generally rises in spring. The decking and its components should therefore ideally sit above the level reached by the rising ice. If this is not possible, the depth of the helical piles in the bed must provide resistance to this uplift during extreme spring events. We recommend at least 1,5 m. In practice, however, this depends on the structure of the bed soil. Removable decking assembled from sections will also make it much easier to cope with rising ice: remove it at the end of winter and watch the floodwaters without worry!

That settles pile length. Pile diameter depends on the current. Naturally, the faster the current and the more intense the ice movement, the larger the diameter should be. The effects of vertical and horizontal loads can be minimized by correctly designing the above-water part of the pier, using properly positioned diagonal braces (horizontal bracing below the decking is undesirable).

Helical piles of different lengths are used along the pier, but their embedment depth in the soil remains the same. In most cases, pile lengths decrease towards the bank and are shortest where the pier continues onto land. Costs can therefore be minimized (this is another reason for measuring depths correctly).

Third, installation begins with preliminary setting out to determine where the holes in the ice will be. The ice is then opened by whatever method is appropriate (this is often labour-intensive, and setting-out strings would get in the way). The helical pile helices must pass freely through each hole. Precise setting out follows, and the piles are screwed in according to these marks. If the piles have been installed correctly, fitting the bracing is generally straightforward.

Fourth and finally, you have calculated and planned everything properly, either yourself or with help from the pile manufacturer and qualified installers. Now you need to decide whether to build the pier yourself or hire someone. If, after reading this, you believe you can do everything yourself with help from friends and so on, we wish you success: the main thing is to choose the right helical pile manufacturer. If the work is beyond your abilities, choose your installers carefully. WINTTEK and its partners will do everything correctly and quickly. Simply contact us in good time so we can arrange everything!