Helical Pile Installation

First, assess whether everything you have done so far has been done correctly. The ideal situation for installers is a house design that includes a pile foundation design based on ground investigation results. They simply carry out the work according to the design. The main thing is to do it professionally.

What if there is no such design and you designed the house yourself? Or the supplier of the house structure says nothing about the foundation? This happens all too often! The foundation is the basis of the house and does not forgive mistakes. A design and the installation method must therefore still underpin the work. For what to consider when choosing installers, see "Helical Pile Installation - How to Avoid Problems". Here we will look at the process itself, whether you do it yourself or hire specialists.

Everything starts with setting out the pile layout. The process is not particularly complicated, but it requires certain rules to be followed, accurate work and a few simple tools. Beforehand, mow the grass, cut down vegetation within the foundation perimeter and remove any piles of materials or other obstructions. Otherwise, the installers may use far more colourful language than you were expecting. Preparing the site is your responsibility.

Setting out is done the traditional way, using stakes and strings. Do not believe empty claims about nanotechnology, satellite navigation and the like being used for this process! The foundation is positioned relative to the site boundaries, buildings and other reference points, according to your objectives and requirements. The building corners are set out first, or the corners of one section if the perimeter is complex. The rest of the building is then set out relative to those initial reference points.

Helical piles are then generally installed at the building's defining corners. Installation begins with a starter pit 150-200 mm deep and a diameter comparable to that of the pile helices.

This is needed only to help the piles "bite", or initially enter the ground. Drilling pilot holes to a depth of 1-1,5 m is unacceptable. It is permissible only where particularly difficult soils occur near the surface, such as sand, so that the helical pile can pass through them without difficulty and reach at least the frost depth.

Do not be alarmed if installers tilt the piles at quite a substantial angle during the initial stage of driving. This helps the helical pile find its designed position. Soil is not uniform, so the pile can drift sideways. Its vertical alignment also has to be established (a deviation of no more than 1-2 degrees is permitted). Incidentally, most videos on this subject show 2 spirit levels on the pile. That is excessive: one is enough if the installer pays proper attention to it. With UBM rigs and other heavy machinery, getting the pile vertical becomes more difficult, which is understandable: a machine has plenty of power but no intelligence!

It is very important that the helical pile reaches load-bearing soil layers. Only then can it carry the calculated load. This is fairly easy to identify: vibration of the pile and ground, deformation of the tube at the pile's upper end, and rotation stopping completely regardless of the force applied.

The pile has now reached refusal. Next, a surveyor's level, laser level or simply a water level is used to establish the required height above the ground, and any excess length is cut off by an appropriate method. Once again, the specialists determine the outcome, not the equipment. Levelling the foundation by unscrewing piles is strongly discouraged!

We recommend cutting piles below the installation holes used for driving. Understand that the piles are not unnecessarily long: this allowance is needed to complete the installation process properly.

The pile is then filled with sand-cement mortar. This prevents oxygen and water from entering the pile and provides additional resistance to horizontal loads. Helical piles with diameters of 108-133 mm can be reinforced internally. However, this is no cure-all. It is much more important to form what is known as a pile group, with piles inside the perimeter and everything tied together with steel channels, timber beams and so on. This provides more effective resistance to wind loads and similar forces, including the antics of guests at your housewarming party.

All that remains is to weld on pile caps, steel channels or similar members to support the wall's base courses. That is it! The foundation is ready, and construction can continue on the very day installation is completed. No settlement period is expected!

What else should you watch for? The pile you selected may keep driving down into the ground until almost nothing remains above it! Or it may stop advancing while continuing to rotate like a mixer. This means it has not reached load-bearing layers. There are essentially two options. First, abandon piles and choose another type of foundation. Installers, and particularly pile sellers, naturally dislike this option: they have incurred costs and will insist on reimbursement. The alternative foundation can also be very expensive. Second, add extensions to the piles and continue driving. Yes, this costs 30-50% more, but we understand that the foundation is the basis of the house. The price of the work is generally calculated according to the work actually performed.

It makes sense to order a trial installation beforehand if you do not have ground investigation results (investigation is expensive and not necessarily conclusive...). This is not an absolute guarantee, but the likelihood of a correct assessment is nevertheless fairly high. You can then choose a foundation based on its cost. A helical pile foundation is not a cure-all: it is simply a quick, inexpensive type of foundation, although often the only possible option.

Piles can be installed manually (which is not a bad thing: it all depends on the specialists!) or mechanically, using specialist machinery such as UBM rigs or powered equipment such as Hercules.

Everything depends on the installers' capabilities and the complexity of the tasks they face. WINTTEK equipment allows self-contained operation in virtually any weather, terrain and season, among existing buildings and vegetation, without electricity, water and so on. We arrive on site fully equipped! The neighbours will not get in the way and may not even understand how you managed to build something beside their fence, without damaging it and, of course, without breaking the law. Or why their buildings are shifting while yours stand firm, much to their annoyance. This all comes down to correct pile foundation technology and its implementation.

You can perform all the helical pile installation work yourself if you have the know-how, practical skills, willingness, time and friends to help. You simply need to follow the proper process. If that is not possible, contact us or our partners.

Our other articles explain the particular features of helical pile installation in winter, pier construction, shoreline reinforcement and fence construction on helical piles, along with much more useful and interesting information on the subject.